Challenger Ultralight Construction Log Book

r>

Date Construction Details Time Required Picture
Click on to Expand
04-Apr-06 Kit received- tail -fuselage – wings. Wing box damaged. Spar crushed in transit. Remainder of kit seems OK. Noted damage on waybill. 1.0 Hour
05-Apr-06 Reported damage to Geri at QCU. Emailed report and pictures. Started unpacking kit. Returned wing box to QCU factory. 4.0 Hours
06-Apr-06 Drilled 5/16″ diameter holes in root tube for shoulder harnesses. Cut sheet metal for nose storage pockets. 1.0 Hour
07-Apr-06 Drilled 1/4″ diameter holes in root tube for flaperon crank. Assembled push/pull rod to aileron slide assembly 2.0 Hours
07-Apr-06 Drilled and riveted seats and seat backs. Added extra middle seat support to front seat. 1.5 Hours
07-Apr-06 Finished upacking fuselage. 1.0 Hour
09-Apr-06 Drilled and rivetted storage pockets in nose. 0.5 Hours
09-Apr-06 Cut, filed, drilled and rivetted into place sheet metal pieces for joining and supporting fabric at tail, nose, and around gear legs. 1.5 Hours
10-Apr-06 Disconnected spine and torque tube at tail end and corrected torque tube interference by bending spine tube back to normal position. It had been bent slightly (1/4″) in shipping. Problem fixed. Partially assembled rudder push/pull rods. Installed FG99 flanges on tail. Cut and installed plate for intercom box on right side of cockpit. Assembled tire and wheels. 4.5 Hours
11-Apr-06 Drilled holes and installed rubber grommets in bracketsalong left side of cockpit for wires and primer tubes going from instrument panel back to the engine and fuel tank. Planned and laid out instrument panel. 2.0 Hours
13-Apr-06 Installed mounting plate for throttle/choke quadrant. Installed sheet metal strips below drag cable holes for brake cable exit hole. Trial installed vertical stabilizer and rudder assembly and drilled 3/16 holes for rivets and hinge brackets. 3.5 Hours
17-Apr-06 Trial installed horizontal stabilizers and elevators and drilled 3/16 holes for rivets and hinge brackets and tail struts. Assembled, drilled and rivetted elevator push rods. 4.5 Hours
18-Apr-06 Filed and sanded tail components. 1.0 Hour
19-Apr-06 Filed and sanded tail components. 1.5 Hours
24-Apr-06 Filed and sanded tail components. Rounded off gusset edges. 2.0 Hours
24-Apr-06 Drilled out cross tubes for Turbulence 15 gallon fuel tank. Redrilled front cross tube and uprights for 10-24 bolts. 1.5 Hours
25-Apr-06 Temporarily installed top door frame, sanded and prepped for paint. Sanded down and prepped for paint large twin tail tubes and tail wheel assembly. Required disassembly tail wheel to paint brackets. 5.0 Hours
28-Apr-06 Spray painted cockpit exposed metal tubes with galvanized metal primer. Spray painted twin tail tubes and tail wheel assembly with primer. 0.5 Hours
30-Apr-06 Finished taping gussets on tail section components. 1.0 Hours
05-May-06 Finished spray painting tail tubes, tail wheel brackets, upper door frame, and cockpit tubes. Installed aluminum belly pan for bottom strobe light. Installed and rivetted tail wheel assembly and upper door frame. 2.5 Hours
08-May-06 Ordered flip-up nose mod option from Steve Busby. Ordered streamlined door mod from Don Sampson 0.5 Hours
11-May-06 Fitted nose cone, drilled holes for mounting screws, cut hole for nose wheel, drilled hole for pitot tube. 3.0 Hours
13-May-06 Worked on right door assembly. 2.0 Hours
14-May-06 Completed framing right door and streamlined fuselage mod behind door. 1.5 Hours
16-May-06 Finished left door and streamlined mod behind door. 3.0 Hours
22-May-06 Installed Turbulence 15 gallon fuel tank. Sanded and primed door frame. 1.5 Hours
23-May-06 Cut slot for rear pax seat belts behind rear seat. 1.0 Hour
23-May-06 Built storage space above fuel tank with aluminum sheet metal and installed hinges and doors behind seat. 3.5 Hours
24-May-06 Primed and painted door frames. 1.0 Hours
26-May-06 Riveted door frames together. 1.5 Hours
26-May-06 Cut lexan and installed right door and hinges. 3.0 Hours
26-May-06 Drilled and clecoed left door. 1.5 Hours
29-May-06 Finished left door lexan and hinges installation. 1.5 Hours
01-Jun-06 Installed lexan cockpit ceiling sheet. 4.0 Hours
02-Jun-06 Cut out instrument panel from 1/8″ aluminum sheet, filed edges, cut out holes for instruments. 4.0 Hours
03-Jun-06 Filed instrument holes to fit and drilled mounting screw holes. 2.0 Hours
08-Jun-06 Began mounting Kuntzleman Hotbox in framework in nose between rudder pedals and began running wires through fuselage. 1.0 Hour
09-Jun-06 Installed more electric wires and tie wrapped. 1.0 Hour
09-Jun-06 Installed Kuntzleman strobe driver box on floor pan under rear seat and wired it to Hotbox. 2.0 Hours
30-Jun-06 Wired strobes with quick connectors. Installed fuel tank level probe and wired it to panel and Hotbox. Installed fuel primer line, Fuel filter, and tee” fitting in fuel line to primer line. 2.0 Hours
08-Jul-30 Finished filing instrument holes. Cut square Hobbs meter hole. Sanded instrument panel, primed and painted. 1.0 Hour
10-Jul-06 Began mounting instruments and electric switches. 1.0 Hour
11-Jul-06 Began wiring up panel instruments and switches. 1.0 Hour
17-Jul-06 Installed 2 EGT and 1 CHT gauges and Hobbs meter. 1.0 Hour
01-Aug-06 Wired up EGT CHT Tach gauges to Hotbox terminal strip. 1.0 Hour
18-Sep-06 Sanded aluminum tubes on fuselage. Removed ink print. 1.0 Hour
22-Sep-06 Covered rudder and vertical stabilizer with fabric and glued. 1.0 Hour
24-Sep-06 Ironed rudder and verticle stabilizer. 1.0 Hour
25-Sep-06 Covered,glued remainder of tail section pieces. 3.0 Hours
18-Oct-06 Ironed remainder of tail section pieces. 2.0 Hours
16-Nov-06 Glued protective fabric tape strips and gap seals on tail pieces. 2.0 Hours
23-Nov-06 More gluing and ironing of tape strips and gap seals on tail. 5.0 Hours
30-Nov-06 Completed fabric on tail. 2.0 Hours
05-Dec-06 Sealed tail components with thinned glue. 1.5 Hours
06-Dec-06 Started main landing gear temporary install. 1.5 Hours
10-Dec-06 Mounted wheels – main gear. 1.5 Hours
11-Dec-06 Drilled main gear axles and mounted nose gear, drilled shaft. 1.5 Hours
13-Dec-06 Cut and mounted 3 fibreglass wheel pants. 4.0 Hours
14-Dec-06 Installed rudder pedal push rods, nose wheel push rods, brake lever on control stick, hand grips on control stick. 2.0 Hours
14-Dec-06 Punched, drilled, trimmed 60 of the W1X rib gussets, started grinding off the sharp corners. 1.5 Hours
16-Dec-06 Finished grinding off the sharp corners of the W1X rib gussets. Also ground off sharp edge on wing rib ends. 1.5 Hours
20-Dec-06 Marked and drilled holes in wing ribs for fabric rivets. 1.0 Hour
22-Dec-06 Finished drilling holes in wing ribs for fabric rivets. 1.5 Hours
27-Dec-06 Fitted nose cone, aligned, layed out cut lines for flip up nose option. 1.0 Hour
01-Jan-07 Built tables for wing construction. Started building wing boxes on right wing. 5.5 Hours
02-Jan-07 Continued work on right wing boxes. 1.5 Hours
03-Jan-07 Finished wing boxes on right wing. 1.0 Hours
03-Jan-07 Installed ribs and leading edge gussets on right wing. 3.0 Hours
04-Jan-07 Finished ribs and trailing edge gussets on right wing. 1.5 Hours
04-Jan-07 Temporarily installed fibreglass wing tip and drilled holes, held with clecos. 2.0 Hours
06-Jan-07 Finished right wing tip. Hung up wing. Started left wing boxes. 1.5 Hours
06-Jan-07 Finished bottom of sheet metal wing boxes at root and wing tip left wing. 1.5 Hours
09-Jan-07 Finished top of sheet metal boxes on left wing. Started rivetting. 3.5 Hours
10-Jan-07 Finished rivetting bottom of wing box and started installing wing ribs on the left wing. 1.5 Hours
12-Jan-07 Installed, drilled and rivetted all ribs for the left wing. 2.0 Hours
12-Jan-07 Started Install of left fibreglass (Hoerner) wing tip.(Temporary with clecos) 1.0 Hours
13-Jan-07 Finished left Hoerner wingtip installation. (Clecoed) 1.5 Hours
14-Jan-07 Primed and spray painted wing strut outside attachment brackets. 0.5 Hours
15-Jan-07 Primed jury struts and spray
ed another coat on wing strut brackets.
0.5 Hours
16-Jan-07 Finished spray painting jury struts and strut brackets. 0.5 Hours
16-Jan-07 Mounted left aileron hinges and aileron assembly with clecoes and checked for proper range of movement. 3.0 Hours
17-Jan-07 Moved wings. Started right wing aileron install. 0.5 Hours
19-Jan-07 Installed right aileron hinges and aileron assembly with clecoes and checked for proper range of movement. 2.0 Hours
16-Feb-07 Installed AeroControls throttle/choke quadrant front and rear cockpit. Ran the cables through holes in the support gussets along the side. 4.0 Hours
19-Feb-07 Installed reinforcing sheet metal to belly and sides. 1.0 Hours
20-Feb-07 Installed receptacles on right side of cockpit for electric heated seats. 1.0 Hours
20-Feb-07 Installed Tiny Tach electronic tachometer to instrument panel and ran wires back to engine along gussets on left side. 2.0 Hours
08-Mar-07 Filed, sanded, covered, and glued both ailerons. 5.0 Hours
11-Mar-07 Added protective tape to ailerons and sealed fabric weave with thinned glue. 5.0 Hours
15-Mar-07 Sanded left wing. Added protective masking tape over gussets and other sharp edges. 1.5 Hours
16-Mar-07 Covered bottom of left wing and ironed fabric 3 stages. 3.0 Hours
17-Mar-07 Trimmed fabric edges on left wing and glued down. 1.5 Hours
18-Mar-07 Covered top of left wing. Ironed first stage 250′F. Trimmed edges and glued them down. Glued ribs. Hot knifed holes for fabric rivets. Redrilled the holes. Taped over the ribs. Rivetted fabric down on all the ribs. 6.0 Hours
25-Mar-07 Started to install fabric protective strips over the ribs. 1.0 Hours
26-Mar-07 Finished installing and gluing down the protective fabric strips over the ribs. Installed the aileron onto the left wing with stainless rivets. Installed 3″ fabric gap seal strip between aileron and wing. Installed 4″ protective fabric strip on leading edge of wing. Ironed top of wing 300′F and 350′F. 5.5 Hours
29-Mar-07 Sealed weave of fabric on top of left wing with thinned glue. 1.5 Hours
30-Mar-07 Sealed fabric weave on bottom of left wing with thinned glue. Added fabric reinforcing patches around area where holes will be cut for strut brackets. 3.0 Hours
01-Apr-07 Sanded right wing. Removed ink marks. 1.0 Hours
02-Apr-07 Masking taped rib brackets. Covered bottom of wing. Ironed 250/300/350′F 3.5 Hours
03-Apr-07 Moved fuel gauge. Removed analogue tachometer. Installed Ammeter into panel. Covered top of wing. Ironed 250/300′F. Poked holes for rivets and pulled all 140 fabric rivets. Started attaching reinforcing fabric strips on ribs on the leading edge side. Installed aileron with clecos. 7.5 Hours
04-Apr-07 Finished Installing reinforcing fabric strips over ribs and ironed down. 3.0 Hours
05-Apr-07 Installed leading reinforcing fabric. Painted wooden doors behind rear seat. 2.0 Hours
06-Apr-07 Ironed top of wing 350′F. Sealed top of wing. Installed aileron gap seal. 2.5 Hours
09-Apr-07 Touch up ironing on bottom to remove glue gobs. Sealed bottom of wing. 1.5 Hours
09-Apr-07 Wired and soldered switches for electric heated seats. Dismantled wing assembly tables. 2.0 Hours
09-Apr-07 Sanded fuselage frame. Began taping over gussets, sharp edges and rivets. 1.5 Hours
11-Apr-07 Finished taping over fuselage rough edges. Replaced belly pan for strobes. Added sheet metal to blend fuselage sides to nose cone. Re-routed throttle cables along side. Mounted throttle cable H clip on deck below engine. Glued fabric onto belly of fuselage. 7.0 Hours
12-Apr-07 Ironed belly fabric 250′F.Trimmed fabric and touched up glue on edges. 1.5 Hours
12-Apr-07 Started covering port side with fabric. 1.5 Hours
13-Apr-07 Finished gluing down port side fabric rear panel. Ironed 250′F. 2.0 Hours
15-Apr-07 Covered starboard rear side. 1.5 Hours
15-Apr-07 Trimmed edges, glued and ironed starboard rear panel 250′F. 1.5 Hours
16-Apr-07 Added front fabric panels to fuselage both sides, trimmed, ironed 250′F. Began adding protective fabric strips. 4.0 Hours
20-Apr-07 Added more protective strips to fuselage and cleaned up glue blobs. 1.5 Hours
24-May-07 Finished protective strips and sealed fuselage with thinned glue. 3.0 Hours
01-Jul-07 Wrapped fuselage in plastic to prep for painting. 2.0 Hours
02-Jul-07 Finished wrapping fuselage in prep for paint. 1.0 Hour
02-Jul-07 Primed fuselage sides and tail pieces with Cecofill. 3.0 Hours
04-Jul-07 Applied second coat of cecofill primer to fuselage and tail pieces. Started bottom of right wing one coat primer. Painted tail struts 2nd and 3rd coats. Started to apply fibreglass flange to flip-up nose cone. 5.0 Hours
05-Jul-07 Applied primer to top of right wing and both sides left wing. 2nd coat primer to right wing. These coats are applied with 4″ foam brush. 4.0 Hours
06-Jul-07 Installed LG9 gear leg inserts. Painted both brakes black. 1.0 Hour
06-Jul-07 Applied 2nd coat primer to left wing with foam brush. 1.5 Hours
11-Jul-07 Cut holes and slots in gear leg plastic streamliner. 3.0 Hours
24-Jul-07 Sanded primer. Glued in fiberglass flange for nose cone mod. Sanded ridge of of wheel pants and filled holes with Bondo. Cut and separated two nose cone halves. 4.0 Hours
25-Jul-07 Sanded wheel pants until ready for primer. Added fiberglass reinforcement to nose conefor elastic retaining strap posts. 2.0 Hours
26-Jul-07 Installed flip-up nose hinge assembly. 1.0 Hour
27-Jul-07 Installed nose cone posts. Sanded nose cone assembly for priming. Filed edge for clearance and smooth open and close action. 1.0 Hour
27-Jul-07 Added 3 coats primer to tail pieces. Added 3 coats of primer to wheel pants and gear leg streamline strut cover. Added 3 coats primer to nose cone. 3.5 Hours
28-Jul-07 Sprayed 3 coats yellow paint to tail pieces. 3.0 Hours
30-Jul-07 Sprayed more coats yellow paint on tail. Sprayed 4 coats blue paint to wheel pants, nose cone and gear leg covers. 6.0 Hours
01-Aug-07 Sprayed gloss coat to bottom of horizontal stabilizer/elevators and one side of rudder and fin. 2.0 Hours
03-Aug-07 Sanded paint on tail pieces. 2.0 Hours
04-Aug-07 Sanded nose cone. 1.0 Hour
06-Aug-07 Gloss coat on one side of rudder. 1.0 Hour
07-Aug-07 Final gloss coat on horizontal stabilizers/elevators. Sprayed more coats on nose cone and wheel pants. 7.0 Hours
08-Aug-07 Sanded nose cone and wheel pants 600 grit. Final coat of blue on nose and wheel pants. Cleaned the spray gun very thoroughly. 4.0 Hours
09-Aug-07 Washed fuselage. 1.0 Hour
10-Aug-07 Sprayed 4 cross coats of Ecofill primer on fuselage and sanded. 3.5 Hours
11-Aug-07 Sprayed 3 cross coats of blue paint on fuselage. Clean painting equipment 2.5 Hours
13-Aug-07 Sprayed more blue paint on fuselage to cover primer. Got some runs in paint. Need to sand and recoat. Primed fiberglass wing tips and mid-wing. gap covers. 4.0 Hours
14-Aug-07 Spray painted wing tips and mid wing gap cover through to final gloss coat. Sprayed gloss coat on one side of fin and rudder assembly. 4.0 Hours
15-Aug-07 Painted gloss coat on second side of fin and rudder. 1.5 Hours
16-Aug-07 Sprayed 4 cross coats of primer on right wing. 3.0 Hours
26-Aug-07 Lightly sanded left wing. Sprayed 4 cross coats primer on left wing. 2.5 Hours
26-Aug-07 Sanded right wing. Sprayed 4 cross coats of yellow paint on right wing. 3.0 Hours
28-Aug-07 Sanded left wing. Sprayed 4 cross coats yellow paint on left wing. 3.5 Hours
03-Sep-07 Sanded and spray painted fuselage gloss coat. It did not gloss up enough. 3.0 Hours
03-Sep-07 Spray painted left wing more covering cross coats then final gloss coat. 4.0 Hours
04-Sep-07 Sanded right wing. Sprayed more covering cross coats then final gloss coat. Cleaned the spray gun thoroughly. 6.0 Hours
07-Sep-07 Sanded fuselage. 2.0 Hours
08-Sep-07 Spray painted fuselage final blue gloss coat. Cleaned spray gun. 2.0 Hours
09-Sep-07 Removed plastic masking from fuselage. 2.0 Hours
12-Sep-07 Installed flip-up nose cone and nose wheel and pant. Began installing velcro strips for upholstery on interior. 2.0 Hours
16-Sep-07 Installed rudder/vertical stabilizer assembly, horizontal stabilizer/elevator assemblies, fin, and rudder cables. Trimmed pitot tube. Installed strut brackets onto fuselage. 5.0 Hours
18-Sep-07 Installed rudder push rods. Note- do this before installing fin! Installed gear leg streamliners. Installed wheel pants and brakes. Connected ASI to pitot tube. 3.0 Hours
25-Sep-07 Installed bottom and top strobe lights. Installed and tensioned landing gear wires and drag wires. 2.0 Hours
02-Oct-07 Cut, fitted and installed lexan wind shield. 3.0 Hours
05-Oct-07 Installed right fiberglass wingtip. Installed nylon door latches. 1.0 Hour
08-Oct-07 Installed left fiberglass wingtip. Installed strut brackets to wings. 1.0 hour
15-Oct-07 Installed vinyl graphics to tail section and yellow “Challenger” logo to sides. 1.5 Hours
3-Nov-07 Started cutting out cockpit upholstery in dark blue denim. 1 Hour
15-May-08 Ordered 582 Engine and re-drive package. 1/2 Hour
Final Total time spent assembling Challenger = about 400.0